strings.skip_to_content
drugitir.si
sl
Menu
  • Osp T5-6 tunnel

Osp T5-6 tunnel

The work is in progress

About the Osp T5-6 tunnel

Originally two tunnels were planned in the Osp Tunnel area, but in later phases the two tunnels were merged into a single 505 m long Osp Tunnel. It is characterised by its steeply sloping location and two areas of low overburden, where preliminary surface measures in the form of the removal of a layer of poor soil and rock and its replacement with cement stabilisation were necessary to ensure underground excavation. 

505
m

Length of the main tunnel

Work on the project

The work is completed

Excavation work

Tunnelling is construction work involving the excavation and removal of material necessary for the construction of a tunnel.

It is carried out in two phases: first the upper part of the tunnel (the calotte) is excavated, followed by the lower part of the tunnel (the step with the floor arch).

Progress of excavation works

0%

The work is completed

Inner lining system

The completed internal lining gives the tunnel a distinctive shape, as it gives the underground space a uniform appearance and a smooth surface. 

The construction of the inner lining system consists of: the floor vault, the foundations of the inner arch, the waterproofing of the tunnel, the longitudinal lateral drains and the inner arch, which is concreted with a movable tunnel formwork. 

Interior lining progress

0%

The work is in progress

Other concrete works

In pre-construction, the term "other concreting works" usually covers all concreting activities that are not directly related to the main tunnel structures, such as primary and secondary arches. These works include: the execution of the fill concrete under the corridor, the kineta wall and the fill concrete above the floor vault. 

Such works often also include adjustments to the concrete structures for the installation of technical systems and are essential to complete the tunnel in accordance with the technical and safety requirements

Progress of other concrete works

0%
24.02.2025

Planned

Tracks

A track on a rigid base: 

Rigid track is a modern form of track that is used successfully all over the world, requires less maintenance compared to conventional shaft track, has a longer life expectancy and provides a more comfortable ride. The use of a rigid track system eliminates the possibility of track geometry errors during maintenance work. The possibility of direct attachment to structures, the lower structural height and weight compared to conventional track, make it the most optimal solution for tunnels and bridges. The expected service life of a track built on a rigid base is 50 to 60 years. 

Track laying progress

0%

Planned

Vehicle network

The tunnel catenary is a key component of the electrification of a railway line, enabling trains to be powered by electricity. After the track has been laid, the construction of the overhead contact line typically includes the following steps and elements: installation of the supporting structure, installation of electrical cables and wires, insulation and protection, and tensioning systems. 

 In tunnels, limited space and specific conditions (e.g. ventilation, humidity, vibration) require the use of specially adapted materials and construction solutions to ensure the durability and reliability of the overhead contact line. 

Progress of vehicle network

0%