strings.skip_to_content
drugitir.si
sl
Menu

Building the Second track

Slovenia's excellent geostrategic location offers outstanding opportunities for the development of logistics activities and the economy as a whole. The second railway line will be modern, fast, safe and environmentally friendly.

Get to know the project

Interactive demonstration of the project

In total, the Second track project consists of 27.1 km of track between Divača and Koper. The line itself has 7 tunnels and 3 viaducts. On the map you can see the route of the Second track connecting Divača and Koper, including the locations of the tunnels and viaducts. 

Open section of the track
Work is in progress
MORE ABOUT THE OPEN SECTION OF THE TRACK

Since 75% of the second track runs through seven tunnels, only a small portion of the track is visible on the surface, specifically in the areas where the track crosses three major valleys—viaducts and the open sections of the track. The entire track has only 5.4 kilometers of railway on the open section. Although the open section does not feature grand structures like tunnels or viaducts, constructing the open track from Divača to Koper is still a major challenge. This is because numerous support structures, embankments, cuts, and culverts need to be built. Special attention is given to the quality of embankment construction and the foundation soil, as settlement is unacceptable due to the rigid base that the track will be laid on in the open section. The construction of just over 5 km of the open track of the second line also represents a unique engineering challenge, as numerous new structures must be built to overcome geological and topographical characteristics, which will connect tunnels to the new railway line along with the viaducts.

Deviation of the track in Divača
Work is in progress
ABOUT THE DEVIATION OF THE TRACK

The deviation of the track in Divača, carried out as part of the second track project of the railway connection between Divača and Koper, involves key adjustments to the existing railway infrastructure to facilitate the construction process. The relocation (deviation) of the railway track in Divača was completed in August 2023. A 900-meter-long track was constructed, rails and switches were installed, and an electric traction system along with signaling, safety, and communication devices were put in place.

The route of the second track intersects with the existing railway route, so the existing track had to be moved to a new path.

In planning the deviation, the highest standards of safety, efficiency, and environmental sustainability were considered.

Tunnel Beka T2
Work is in progress
ABOUT TUNNEL BEKA T2

It is the second-longest tunnel on the route, measuring 6,017 meters. The main and service tunnels are connected by 13 cross-passages. The tunnel mainly runs through carbonate rocks (about ¾ of the length), with a smaller part running through transitional layers at both ends of the tunnel and also in intermediate layers of carbonate rock. The construction uses the NATM (New Austrian Tunneling Method) technology, which involves digging and blasting, rather than boring.

Tunnel Škofije T8
Work is in progress
ABOUT TUNNEL ŠKOFIJE T8

This is the third-longest twin-tube tunnel, measuring 3,808 meters. The main and service tunnels are connected by 7 cross-passages. Excavation technology in the flysch foundation was performed mechanically with tunnel excavators, hydraulic hammers, and drilling and blasting. In the area of low overburden in the Škofijica Stream valley, preliminary measures were necessary to remove poor soil above the tunnel and replace it with cement stabilization, followed by the construction of a reinforced concrete arch cover.

Viaduct Vinjan
Work is in progress
ABOUT VIADUCT VINJAN

The Vinjan railway viaduct is the longest on the second track, at 620 meters. The viaduct is designed as a valley viaduct, spanning the Vinjan valley with piers up to 60 meters high and spans of 100 meters. Technologically and organizationally, it is the most complex of the three viaducts on the route of the second track.

Viaduct Gabrovica
Work is in progress
ABOUT VIADUCT GABROVICA

The Gabrovica viaduct runs beneath the Črni Kal highway viaduct, both designed by the renowned engineer Marjan Pipenbaher, which is why their style is quite similar. The railway viaduct runs

The method used to construct the Gabrovica viaduct with incremental launching represents an innovative technique. Pre-stressed reinforced concrete segments are fabricated in a workshop and then pushed forward over supporting piers. This advanced technology allows builders to construct the viaduct gradually, without traditional formwork supports, contributing to a faster and safer project execution.

Viaduct Glinščica
Work is in progress
ABOUT VIADUCT GLINŠČICA

The construction of the Glinščica viaduct was a prerequisite for the start of tunnel construction at Lokev (T1) and Beka (T2) from both sides. It is designed as a closed box-shaped reinforced concrete structure. Its innovative design allows proper ventilation for tunnels Lokev (T1) and Beka (T2), and provides protection against derailments, wind, noise, and emissions in the protected Beka Landscape Park. The Glinščica viaduct will connect the first tunnel, Lokev, the longest at 6.7 kilometers, with the second Beka tunnel, which is 6 kilometers long, forming a continuous tunnel of nearly 13 kilometers.

Tunnel Mlinarji T7
Work is in progress
ABOUT TUNNEL MLINARJI T7

Tunnel T7, or Mlinarji Tunnel, is named after the settlement of Mlinarji nearby. At 1,154 meters in length, it is one of the medium-length tunnels on the second track. It is constructed as a single-tube tunnel, with a cross-side service or escape tunnel 165 meters long at its center. There are no residential buildings within the area affected by the tunnel construction.

Tunnel Osp T5-6
Work is in progress
ABOUT TUNNEL OSP T5-6

Initially, two tunnels were planned in the area of the Osp tunnel, but in later phases, the two tunnels were merged into a single tunnel of 505 meters.

Its uniqueness lies in its steep location and two areas of low overburden, where pre-excavation measures were needed on the surface to remove poor soil and rock above the tunnel and replace it with cement stabilization.

Tunnel Tinjan T4
Work is in progress
ABOUT TUNNEL TINJAN T4

The Tinjan Tunnel is a single-tube tunnel and, at 1,949 meters, is the fourth-longest on the second track. It also has two exit tunnels. Excavation work in the tunnel began in June 2022 and finished in February 2024. No residential buildings are within the area affected by the tunnel construction.

Tunnel Stepani T3
Work is in progress
ABOUT TUNNEL STEPANI T3

This is the shortest tunnel on the second track, at 335 meters, and is the first tunnel coming from Divača, under the Karst edge. Together with the Osp Tunnel (T5-6), it is considered one of the short tunnels, which do not require forced ventilation and escape routes that are needed in medium and long tunnels, provided through side exit tunnels or cross-passages in a parallel service tube. No residential buildings are within the area affected by the tunnel construction.

Tunnel Lokev T1
Work is in progress
ABOUT TUNNEL LOKEV T1

At 6,714 meters, it is the longest tunnel on the new track. Together with the Beka (T2) and Škofije (T8) tunnels, it is a twin-tube tunnel, meaning that a service tunnel runs parallel to the main tunnel, with the same cross-section. In the Lokev Tunnel (T1), at intervals of up to 500 meters, the two tunnels are connected by 13 cross-passages, which provide safe evacuation in case of an emergency via escape and intervention routes, allow for effective maintenance, and provide space for the installation of electrical and mechanical equipment, signaling and safety devices, and firefighting water systems.

  • Tunnel
  • Viaduct
  • Open track
  • Deviation

What does the Second Track solve

Providing a modern, efficient rail link between the freight port of Koper and the European rail network, including removing constraints and increasing the capacity of the line to Divača, which will improve the reliability, safety, environmental sustainability of transport, speed up journeys, reduce environmental impacts and encourage the use of rail transport. 

160
km/h

Maximum speed of passenger trains 

120
km/h

Maximum speed of freight trains 

17
minutes

Travel time (passenger train) - currently 45 minutes 

212
trains

Increased number of trains - previously 90 trains 

36,9
million tonnes

Increased number of freight - previously 12.7 million tonnes