Building the Second track
Slovenia's excellent geostrategic location offers outstanding opportunities for the development of logistics activities and the economy as a whole. The second railway line will be modern, fast, safe and environmentally friendly.
Scroll down
Interactive demonstration of the project
In total, the Second track project consists of 27.1 km of track between Divača and Koper. The line itself has 7 tunnels and 3 viaducts. On the map you can see the route of the Second track connecting Divača and Koper, including the locations of the tunnels and viaducts.
Open section of the track
MORE ABOUT THE OPEN SECTION OF THE TRACK
Since 75% of the second track runs through seven tunnels, only a small portion of the track is visible on the surface, specifically in the areas where the track crosses three major valleys—viaducts and the open sections of the track. The entire track has only 5.4 kilometers of railway on the open section. Although the open section does not feature grand structures like tunnels or viaducts, constructing the open track from Divača to Koper is still a major challenge. This is because numerous support structures, embankments, cuts, and culverts need to be built. Special attention is given to the quality of embankment construction and the foundation soil, as settlement is unacceptable due to the rigid base that the track will be laid on in the open section. The construction of just over 5 km of the open track of the second line also represents a unique engineering challenge, as numerous new structures must be built to overcome geological and topographical characteristics, which will connect tunnels to the new railway line along with the viaducts.
Deviation of the track in Divača
ABOUT THE DEVIATION OF THE TRACK
The deviation of the track in Divača, carried out as part of the second track project of the railway connection between Divača and Koper, involves key adjustments to the existing railway infrastructure to facilitate the construction process. The relocation (deviation) of the railway track in Divača was completed in August 2023. A 900-meter-long track was constructed, rails and switches were installed, and an electric traction system along with signaling, safety, and communication devices were put in place.
The route of the second track intersects with the existing railway route, so the existing track had to be moved to a new path.
In planning the deviation, the highest standards of safety, efficiency, and environmental sustainability were considered.
Tunnel Beka T2
ABOUT TUNNEL BEKA T2
It is the second-longest tunnel on the route, measuring 6,017 meters. The main and service tunnels are connected by 13 cross-passages. The tunnel mainly runs through carbonate rocks (about ¾ of the length), with a smaller part running through transitional layers at both ends of the tunnel and also in intermediate layers of carbonate rock. The construction uses the NATM (New Austrian Tunneling Method) technology, which involves digging and blasting, rather than boring.
Tunnel Škofije T8
ABOUT TUNNEL ŠKOFIJE T8
This is the third-longest twin-tube tunnel, measuring 3,808 meters. The main and service tunnels are connected by 7 cross-passages. Excavation technology in the flysch foundation was performed mechanically with tunnel excavators, hydraulic hammers, and drilling and blasting. In the area of low overburden in the Škofijica Stream valley, preliminary measures were necessary to remove poor soil above the tunnel and replace it with cement stabilization, followed by the construction of a reinforced concrete arch cover.
Viaduct Vinjan
ABOUT VIADUCT VINJAN
The Vinjan railway viaduct is the longest on the second track, at 620 meters. The viaduct is designed as a valley viaduct, spanning the Vinjan valley with piers up to 60 meters high and spans of 100 meters. Technologically and organizationally, it is the most complex of the three viaducts on the route of the second track.
Viaduct Gabrovica
ABOUT VIADUCT GABROVICA
The Gabrovica viaduct runs beneath the Črni Kal highway viaduct, both designed by the renowned engineer Marjan Pipenbaher, which is why their style is quite similar. The railway viaduct runs
The method used to construct the Gabrovica viaduct with incremental launching represents an innovative technique. Pre-stressed reinforced concrete segments are fabricated in a workshop and then pushed forward over supporting piers. This advanced technology allows builders to construct the viaduct gradually, without traditional formwork supports, contributing to a faster and safer project execution.
Viaduct Glinščica
ABOUT VIADUCT GLINŠČICA
The construction of the Glinščica viaduct was a prerequisite for the start of tunnel construction at Lokev (T1) and Beka (T2) from both sides. It is designed as a closed box-shaped reinforced concrete structure. Its innovative design allows proper ventilation for tunnels Lokev (T1) and Beka (T2), and provides protection against derailments, wind, noise, and emissions in the protected Beka Landscape Park. The Glinščica viaduct will connect the first tunnel, Lokev, the longest at 6.7 kilometers, with the second Beka tunnel, which is 6 kilometers long, forming a continuous tunnel of nearly 13 kilometers.
Tunnel Mlinarji T7
ABOUT TUNNEL MLINARJI T7
Tunnel T7, or Mlinarji Tunnel, is named after the settlement of Mlinarji nearby. At 1,154 meters in length, it is one of the medium-length tunnels on the second track. It is constructed as a single-tube tunnel, with a cross-side service or escape tunnel 165 meters long at its center. There are no residential buildings within the area affected by the tunnel construction.
Tunnel Osp T5-6
ABOUT TUNNEL OSP T5-6
Initially, two tunnels were planned in the area of the Osp tunnel, but in later phases, the two tunnels were merged into a single tunnel of 505 meters.
Its uniqueness lies in its steep location and two areas of low overburden, where pre-excavation measures were needed on the surface to remove poor soil and rock above the tunnel and replace it with cement stabilization.
Tunnel Tinjan T4
ABOUT TUNNEL TINJAN T4
The Tinjan Tunnel is a single-tube tunnel and, at 1,949 meters, is the fourth-longest on the second track. It also has two exit tunnels. Excavation work in the tunnel began in June 2022 and finished in February 2024. No residential buildings are within the area affected by the tunnel construction.
Tunnel Stepani T3
ABOUT TUNNEL STEPANI T3
This is the shortest tunnel on the second track, at 335 meters, and is the first tunnel coming from Divača, under the Karst edge. Together with the Osp Tunnel (T5-6), it is considered one of the short tunnels, which do not require forced ventilation and escape routes that are needed in medium and long tunnels, provided through side exit tunnels or cross-passages in a parallel service tube. No residential buildings are within the area affected by the tunnel construction.
Tunnel Lokev T1
ABOUT TUNNEL LOKEV T1
At 6,714 meters, it is the longest tunnel on the new track. Together with the Beka (T2) and Škofije (T8) tunnels, it is a twin-tube tunnel, meaning that a service tunnel runs parallel to the main tunnel, with the same cross-section. In the Lokev Tunnel (T1), at intervals of up to 500 meters, the two tunnels are connected by 13 cross-passages, which provide safe evacuation in case of an emergency via escape and intervention routes, allow for effective maintenance, and provide space for the installation of electrical and mechanical equipment, signaling and safety devices, and firefighting water systems.
-
Tunnel
-
Viaduct
-
Open track
-
Deviation
News about Second track
Keep up to date with the progress of Second track.
The company 2TDK at the international professional project management conference.
The Second Track project remains within the investment values defined in the Investment Program (NIP2).
The management of 2TDK is today visiting the construction site of the Second Track
What does the Second Track solve
Providing a modern, efficient rail link between the freight port of Koper and the European rail network, including removing constraints and increasing the capacity of the line to Divača, which will improve the reliability, safety, environmental sustainability of transport, speed up journeys, reduce environmental impacts and encourage the use of rail transport.
Maximum speed of passenger trains
Maximum speed of freight trains
Travel time (passenger train) - currently 45 minutes
Increased number of trains - previously 90 trains
Increased number of freight - previously 12.7 million tonnes