Progress on the Second Track (video)
⚒Tunnels
✅ Excavation work – completed
✅ Inner lining – 75%
✅ Other concrete works – 30%
🏗Viaducts
✅Main construction works – completed
🛤Tracks
✅1350 m of track laid on a rigid foundation