🚆 Section 1, which runs from Divača to Črni Kal, contains the two longest tunnels on the route, both over 6 kilometers long

🚇 In the Lokev Tunnel (T1), the interior lining has been completed, and track work is already underway

🏗 A ventilation station is being built in front of the Beka Tunnel (T2)

⛏ More than 90 karst features have been identified along this karst section of the route

🚧 Landslide remediation is underway in the Glinščica Valley

🌍 The tunnels are connected by the Glinščica Viaduct, with special attention being paid to environmental protection in the Beka Landscape Park

🛤 Getting closer and closer to a faster, safer, and more sustainable future