2TDK did not approve the expense of 714,000 euros

23. October 2026

2TDK rejects the claims published on the “Dnevnik” program on TV Slovenija and on the MMC RTV Slovenija website on October 23, 2026, that it had approved the cost of the March test run on the second track in the amount of 714,000 euros.

Submitting claims for additional payments is standard practice in the implementation of construction projects in Slovenia, abroad, and on the Second Track project.

The company SŽ-Železniško gradbeno podjetje Ljubljana, d. d., submitted a claim dated May 5, 2026, and a supplement dated June 24, 2026, regarding the assurance of track operability, and also forwarded them to 2TDK for information.

The amount in the original claim, due to the temporary suspension of work, was 55,853.42 EUR excluding VAT, while the supplement to the claim, aimed at accelerating the completion of track work, amounted to 652,259.36 EUR.

Claims are subject to a multi-stage expert review before the investor, 2TDK, decides whether to approve them. The mere submission of a claim does not guarantee that it will be approved, nor does it mean that the contractor will be entitled to the full amount claimed.

2TDK has not yet received a draft decision from DRI regarding the validity of the claim.

Furthermore, 2TDK never stated that it would present details about the claims next week, as reported in the TV Slovenija segment. Due to the aforementioned false information, 2TDK has submitted an official request to RTV Slovenia to publish a correction. To ensure the public is fully and transparently informed, we are publishing the text of the requested correction, along with the original journalistic questions and 2TDK’s complete response, which clearly shows what information was provided to RTV Slovenia.

Attachments:

  • Request for publication of a correction, including the text of the correction

  • Questions from RTV Slovenia journalists and 2TDK’s full response